Expect road work for the next four weeks on Interstate 17 between New River and Sunset Point Alternating lane restrictions expected overnight in both directions

Crews have completed the initial paving on Interstate 17 between New River and Sunset Point as part of a $10.8 million pavement project that began last summer. However, crews will be on site over the next four weeks as they work on sign and guardrail installations, delineators and other miscellaneous work.

Work is scheduled to occur Sunday through Thursday nights from 6:30 p.m. to 6 a.m. Drivers should anticipate north and southbound lane restrictions during work hours.

The project is scheduled to be completed by summer 2017.

Drivers should proceed through the work zone with caution, slow down and watch for construction personnel and equipment.

For the most current information about highway conditions statewide, visit the ADOT Traveler Information site atwww.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving. For more information about this project, please call Tricia Lewis, senior community relations officer, 928.606.2420 or email tlewis@azdot.gov.

No comments:

Post a Comment

Click On Picture To Order

Click On Picture To Order
Support Desert Radio AZ

IS HE WORTH THE EFFORT?

Okay, so you're not Helen of Troy, Cleopatra, Marilyn Monroe, or some other great sex goddess of the past or present -- but you'd st...